| Building
Deconstruction: Reuse and Recycling of Building Materials
Prepared
by:
Powell Center for Construction and Environment, University of
Florida
PO
Box 115703, Gainesvil\-le, Florida USA 32611-5703,
Tel: (352)-392-7502
On
behalf of:
Alachua
County Solid Waste Management Innovative Recycling
Project, August, 2000
Acknowledgements
The
Construction Site Supervisor for this project was
Mr. Kevin Ratkus. Data Collection was performed
by Mr. Sean McLendon and Mr. Bradley Guy. The Principal
Author of this report was Mr. Bradley Guy, including
materials prepared by Mr. Sean McLendon.
ABSTRACT
The
PCCE deconstructed six (6) houses during 1999-2000
to examine the cost-effectiveness of deconstruction
and salvage when compared to traditional demolition.
This research was funded through the Florida Department
of Environmental Protection (FDEP) Innovative Recycling
Projects grant program through Alachua County. The
one and two-story houses that were deconstructed
represent typical Southeastern US wood-framed residential
construction from 1900 to 1950. Regulatory issues
included the costs and implementation of environmental,
demolition, and historic permitting practices in
the Gainesville / Alachua County, Florida region,
and handling of lead-based paint (LBP) materials,
and asbestos containing materials (ACM). Worker
safety issues and technical issues included protection
from environmental and site hazards and a case-by-case
materials management process for each building.
Reuse and materials redistribution scenarios include
on-site and off-site redistribution and associated
costs and benefits. Over 500 pieces of salvaged
lumber were visually graded by the Southern Pine
Inspection Bureau, to understand the damage of
use and the deconstruction process on salvaged lumber
in reducing use in structural applications.
KEYWORDS:
deconstruction, selective dismantling, C&D wastes
management, building salvage, building materials
reuse.
Project
Background
From
August, 1999 to May, 2000 the Powell Center for Construction and Environment, University of Florida, with funding
from Alachua County Public Works Division and the
Florida Department of Environmental Protection (FDEP)
deconstructed six (6) wood-framed residential structures
in Gainesville, Florida. University students provided
labor on the first three buildings and Americorps*NCCC
members worked on the second three. Houses were
acquired mainly through word of mouth. Permitting
processes included issues of historic preservation,
demolition delay requirements, licensed contractor
requirements and environmental, safety and health
certifications for hazardous materials management,
utility disconnections, and septic tank removals.
Each house was tested for lead-based paint (LBP)
and asbestos containing material (ACM). All structures
were completely removed from the site, comparable
to a total demolition. Time and activity data was
collected for each worker and all associated costs
and estimated revenues from salvaged materials were
calculated. Each building was also estimated for
demolition in order to make a comparison with deconstruction
and salvage. There was considerable variety in the
buildings’ conditions, the location of the buildings,
and the efficiency of each deconstruction.
Buildings
Summary
The
structures ranged from approximately 1000 to 2000
SF and were both single and two-story. The oldest
structure was built in 1900 and the youngest built
in 1950. The typical construction was a raised wood
floor structure on brick and/or concrete piers,
light wood wall-framing, roof rafters, and interior
and exterior wood cladding and sheathing. Two structures
had plaster and lathe interior wall finishes. In
one case gypsum wallboard was applied directly over
the wood beadboard interior wall finish. One structure
also had two roof finishes, metal over asphalt shingles,
and two floor finishes, an oak floor laid directly
on top of a pine floor. All of the structures had
rot from water damage principally in kitchen or
bath floor areas, but also including wall areas
at leaks from the roof.
Table
One - Summary of Buildings
|
Building address #
|
2930
|
711
|
14
|
2812
|
901
|
3650
|
|
Built
|
1915
|
1945
|
1900
|
1900
|
1920’s
|
1950
|
|
Stories
|
1
|
2
|
2
|
1
|
1
|
1
|
|
Light
framed wood construct.
|
Y
/ CMU
|
Y
|
Y
|
Y
|
Y
|
Y
|
|
Size
(SF)
|
2,014
|
1,436
|
2,059
|
1,238
|
992
|
1,118
|
|
Urban
or rural-sized parcel
|
Rural
|
Urban
|
Urban
|
Rural
|
Rural
|
Rural
|
|
Additions
|
Y
|
Y
|
Y
|
Y
|
Y
|
Y
|
|
#
of additions
|
3
|
1
|
1
|
2
|
3
|
1
|
|
Internal
renovations
|
Y
|
N
|
Y
|
N
|
Y
|
N
|
|
Inhabitable
|
Y
|
N
|
Y
|
N
|
Y
|
Y
|
|
Require
major repair
|
N
|
Y
|
N
|
Y
|
N
|
N
|
| Asbestos
|
|
|
|
|
|
|
|
Exterior
wall finish
|
Y
|
N
|
N
|
N
|
N
|
N
|
|
Roofing
|
N
|
N
|
Y
|
N
|
N
|
N
|
|
Insulation
|
N
|
N
|
Y
|
N
|
N
|
N
|
|
Floor tile
|
Y
|
N
|
Y
|
N
|
N
|
Y
|
|
Drywall
|
N
|
N
|
Y
|
N
|
N
|
N
|
| Abatement
|
Y
|
N
|
Y
|
N
|
N
|
Y
|
| Lead-based
paint |
|
|
|
|
|
|
|
Interior
trim
|
N
|
N
|
Y
|
Y
|
N
|
N
|
|
Exterior
trim
|
Y
|
Y
|
N
|
Y
|
N
|
Y
|
| Interior
surfaces |
N
|
Y
|
N
|
N
|
Y
|
N
|
| Exterior
surfaces |
N
|
Y
|
Y
|
N
|
Y
|
Y
|
| Reason
for removal |
|
|
|
|
|
|
|
Redevelopment
site
|
Y
|
|
Y
|
Y
|
Y
|
|
|
Taxes
/ expense
|
|
|
|
|
|
Y
|
|
Safety
/ disuse
|
|
Y
|
|
|
|
|
|
Homeless
/ fire hazard
|
|
|
|
Y
|
|
|
All
of the structures had additions, and these were
typically for; 1) adding enclosed living space,
2) adding kitchen and bathroom facilities on older
structures, 3) enclosing an existing open porch
area. Four (4) out of six (6) could be made habitable,
and three (3) of six (6) had been recently occupied
prior to the building’s removal. One (1) house
had been occupied by homeless persons without
heating, kitchen, or bathroom facilities. Three
(3) of the six (6) structures were found to have
asbestos containing materials (ACM) requiring
abatement. Two
(2) of the structures contained only non-friable
asbestos which could have been “wet demolished”
by mechanical means but would have required the
entire demolition wastes load to be disposed off
in a hazardous materials landfill. Only one building
had LBP only on the inside, typically LBP was
found on exterior window and door trim, where
it was used in gloss and semi-gloss paint for
durability.
Two
(2) of the six (6) buildings were on property
slated for immediate commercial or multi-family
redevelopment, two (2) were on property slated
for long-term redevelopment, and two (2) buildings
were on land not slated for redevelopment. The
latter two (2) structures may have been left vacant
for an indeterminate length of time if they had
not been used for this project. During the course
of the project, one building verbally committed
to the deconstruction project, on a site slated
for commercial redevelopment, was demolished.
In addition, two candidate buildings, on sites
slated for redevelopment, were moved. One structure
that was considered for the project was considered
too dilapidated for a reasonable deconstruction
and another was passed over due to scheduling
conflicts and was subsequently partially renovated
by the owner. The average size of the six structures
was 1,476 SF.
Based
upon literature review and anecdotal information,
this sample of structures would appear to be representative
of residential demolitions in the United States.
Also, approximately 94% of all residential buildings
built each year in the US are light wood-framed
construction (NAHB, 1994).
Data
Collection
On-site
labor was documented by recording each worker’s
activities on a 15-minute time increment.
There have been several well-documented
deconstruction pilot projects in the US with this
detail of data collection, most notably the Fort
Ord Pilot Deconstruction project conducted by
the Fort Ord Reuse Authority (Cook, 1997) and the Riverdale Pilot Deconstruction
Project conducted by the National Association
of Home Builders Research Center
(NAHBRC, 1997). These projects provided
models for creating the data collection process.
Data is divided into two categories; the deconstruction
of the structure and the processing of the salvaged
materials. The cost of a traditional demolition
was calculated for each structure, including disposal
costs. Salvage revenues were estimated using a
percentage (25-50%) of retail prices from local
building materials suppliers and the experience
of a former used building materials store owner/operator
in Gainesville, Florida. Disposal costs were estimated
by weight and costs data provided by the wastes
haulers for the project.
Worker
labor activities were sub-divided into categories
by the location in, or component of, the building
in order to calculate the costs of deconstructing
a particular component of the building, and the
costs to salvage a unit of a particular material.
The latter information was used to assign a unit
cost of extraction and processing that could be
compared to the pricing units for materials, i.e.
number, linear feet, or board foot of material.
Labor productivity data was collected in the following
task categories:
(S)
upervision
Directing
and planning the flow of work on the job site.
(Decon)
struction
Labor
involved in the initial removal of materials from
the structure. Any manual or mechanical procedure
required to remove materials for salvage, either
the direct handling of a material or removing
other materials to gain aPCCEss to the salvage
material.
(Demo) lition
The
hand or mechanical removal of building materials
for direct disposal.
(P)
rocessing
Preparing
materials for redistribution in reusable form.
Denailing is the most typical processing
activity.
(N)
on-production
No
work is being performed. Includes breaks and the
unloading and clean-up of daily tools, but excludes
lunch.
(C)
lean-up / (Dis) posal
Sweeping
and/or removing debris or demolition materials
from a work area and/or disposal into a roll-off
container.
L)
oading/unloading
Loading
or unloading materials from the site onto a truck
for transport and at the final storage area.
The
largest percentage of time on any deconstruction
was the deconstruction activity, an average of
26% of total time. The next greatest percentage
of time was spent in processing materials at an
average of 21%. Disposal and cleaning required an average of
17% of total time. Demolition required an average
of ~12% of total time. The house with the largest
percentage of time spent for deconstruction was
the house at 901 SR 301 (47.8%). This house was
being removed for redevelopment and had a very
short time frame for the deconstruction. It was
also located on a major highway in the corner
of a shopping center site, and materials were
redistributed by placing them neatly in separate
piles at the site and posting “Free Materials”
signs to encourage passersby to remove the materials
themselves. All of the materials were removed
within one day after the completion of the deconstruction.
Table
Two - Sample Data Sheet
|
Location:
|
|
|
|
Completed by:
|
|
Date:
|
|
Worker
|
#1
|
#2
|
#3
|
#4
|
#5
|
#6
|
#7
|
|
7:30
|
|
|
|
|
|
|
|
|
Activity
|
|
|
|
|
|
|
|
|
Room
|
|
|
|
|
|
|
|
|
Location
|
|
|
|
|
|
|
|
|
Material
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Activity
|
Supervise
|
Decon
|
Process
|
Demo
|
|
|
|
|
|
S
|
Dec
|
P
|
Dem
|
|
|
|
|
|
Clean/Disposal
|
Non-Prod
|
Load
|
|
|
|
|
|
C/Dis
|
|
N
|
L
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Location
|
Site
|
Wall trim
|
Cabinet
|
Fixtures
|
Int W Fin
|
Ceil Fin
|
NL Int W
|
|
|
Wall Cav
|
Attic
|
Floor Str
|
Roof Sh
|
Roof Str
|
Ext W tr
|
Ext W Fin
|
|
|
Ext W sh
|
Ext W Str
|
Floor Fin
|
Subfloor
|
Roof trim
|
Roof Fin
|
Chimney
|
|
|
Found
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Material
|
Debris
|
1x3
|
1x4
|
1x5
|
Wood
|
Metal
|
Hardware
|
|
|
E Panel
|
Outlet
|
Wire/Pipe
|
Tin
|
Tar paper
|
1x6
|
4x4
|
|
|
1x3 Wd flr
|
2x4
|
1x8
|
1x10
|
2x10
|
2x12
|
1x4 Wd flr
|
|
|
Bldg paper
|
4x6
|
4x8
|
4x10
|
4x12
|
6x
|
Drywall
|
|
|
Pl/Lathe
|
Beadbd
|
1x12
|
2x6
|
2x8
|
Brick
|
Concrete
|
|
|
Arch Salv
|
|
|
|
|
|
|
The
house with the lowest percentage of time in deconstruction
was the house at 711 NW 7th Avenue
(12%). This structure was in the poorest condition
of any of the structures and therefore had the
lowest amount of salvage. Commensurately, this
building had the highest percentage of time spent
in disposal and cleaning (39.6%). Excluding the
house at 711 NW 7th Avenue which had
a very low salvage rate and very little processing
(4.3%), processing was a relatively consistent
percentage of time between 18 – 30% of total time.
The house at 711 NW 7th Avenue had
the highest percentage of time spent in demolition,
consistent with low deconstruction and high disposal
and cleaning efforts.
Table
Three - Labor Time by Work Categories
|
Category Hours
|
|
|
|
|
|
|
|
|
|
|
|
|
S
|
Dec
|
P
|
Dem
|
Dis/C
|
N
|
L
|
Total
|
|
2930
|
hr
|
60.50
|
179.50
|
204.80
|
0.00
|
100.00
|
52.75
|
80.00
|
677.55
|
|
2014 SF
|
%
|
8.93
|
26.49
|
30.23
|
0.00
|
14.76
|
7.79
|
11.81
|
|
|
per SF
|
hr
|
0.030
|
0.089
|
0.102
|
0.000
|
0.050
|
0.026
|
0.040
|
0.336
|
|
711
|
hr
|
20.50
|
24.33
|
8.67
|
42.95
|
80.50
|
14.33
|
12.25
|
203.53
|
|
1436 SF
|
%
|
10.07
|
11.95
|
4.26
|
21.10
|
39.55
|
7.04
|
6.02
|
|
|
per SF
|
hr
|
0.014
|
0.017
|
0.006
|
0.030
|
0.056
|
0.010
|
0.009
|
0.142
|
|
14
|
hr
|
62.13
|
113.56
|
124.56
|
26.67
|
81.00
|
27.00
|
42.87
|
477.79
|
|
2059 SF
|
%
|
13.00
|
23.77
|
26.07
|
5.58
|
16.95
|
5.65
|
8.97
|
|
|
per SF
|
hr
|
0.030
|
0.055
|
0.060
|
0.013
|
0.039
|
0.013
|
0.021
|
0.232
|
|
2812
|
hr
|
29
|
133.13
|
217.63
|
39.13
|
63.25
|
53.75
|
21.5
|
557.39
|
|
1238 SF
|
%
|
5.20
|
23.88
|
39.04
|
7.02
|
11.35
|
9.64
|
3.86
|
|
|
per SF
|
hr
|
0.023
|
0.108
|
0.176
|
0.032
|
0.051
|
0.043
|
0.017
|
0.450
|
|
901
|
hr
|
11.75
|
124.75
|
47
|
27
|
25.75
|
23
|
1.75
|
261.00
|
|
992 SF
|
%
|
4.50
|
47.80
|
18.01
|
10.34
|
9.87
|
8.81
|
0.67
|
|
|
per SF
|
hr
|
0.012
|
0.126
|
0.047
|
0.027
|
0.026
|
0.023
|
0.002
|
0.263
|
|
3650
|
hr
|
16
|
84
|
91.85
|
64.5
|
35
|
50.5
|
17.25
|
359.10
|
|
1118 SF
|
%
|
4.46
|
23.39
|
25.58
|
17.96
|
9.75
|
14.06
|
4.80
|
|
|
per SF
|
hr
|
0.014
|
0.075
|
0.082
|
0.058
|
0.031
|
0.045
|
0.015
|
0.321
|
|
|
|
|
|
|
|
|
|
|
|
|
Average %
|
|
7.69
|
26.21
|
23.86
|
10.34
|
17.04
|
8.83
|
6.02
|
100.00
|
|
Average per SF
|
|
0.021
|
0.078
|
0.079
|
0.027
|
0.042
|
0.027
|
0.017
|
0.291
|
The
deconstruction process roughly follows the reverse
of the construction process. The materials that
have been put on last will come off first. Variations
occur between whole building sections, for example,
an addition will be removed in its entirety separately
from the rest of the building. The practice of
focusing on each material type in a reverse order
of the construction process is more efficient
for separating materials for reuse, recycling,
and disposal at the time of removal. Additions
are an impediment to removing one type of material
or whole sections of the original structure, but
can provide a working surface for other parts
of the building, and be structurally dependent
on other parts of the building. For these reasons,
additions were typically removed in their entirety,
regardless of breaking up the material-by-material
consistency of the deconstruction process.
Economics
The
net cost of the deconstruction is modeled by the
expression:
(Deconstruction + Disposal + Processing) – (Contract
Price + Salvage Value) = Net Deconstruction Costs.
The net cost for demolition is:
(Demolition + Disposal) – (Contract Price) = Net
Demolition Costs. If materials are not resold
or redistributed on-site or reused by the deconstruction
contractor in new construction, transportation
and storage costs may be additional costs for
deconstruction. In order for deconstruction to
be cost-effective and competitive with traditional
demolition and disposal, the sum of the savings
from disposal and revenues from resale of materials,
must be greater than the incremental increase
in labor cost for deconstruction versus demolition.
There
are multiple options for contracts and costs/revenues
between a building owner and the deconstruction
contractor, such as:
-
Deconstruction
as a service to the building Owner and the Owner
retains ownership of the salvaged materials.
This can also be a guaranteed “buy back” of
the materials and treated according, with some
consideration for the Contractor’s costs for
processing and handling. The Owner will pay
more than demolition but could be “buying” very
high value materials.
-
Deconstruction
with shared ownership of the materials, with
a reduction in the deconstruction contract based
upon the Contractor receiving materials as in-kind
payment.
-
Deconstruction
with the Contractor retaining all materials,
and charging an internally calculated price
based upon revenues to be received from resale
of salvaged materials.
-
A non-profit deconstructor
performs a deconstruction for a fee and the
Owner donates the materials as a tax write-off.
An
economic factor for deconstruction on a redevelopment
site is the time costs of money in financing and
construction loan interests. A large site may
allow an unwanted structure to be isolated from
the other construction activity and be deconstructed
without delaying the site development. In the
case of a site where the new construction will
take place on the footprint of the existing structure,
the time for removal of the existing structure
by deconstruction is a significant economic impediment.
Permitting
The
City of Gainesville has a unique demolition permitting
process which allows the City to place a 90-day
demolition delay on any residence that may have
historic value (older than 45 years). During this
90-day delay, the structure is posted as free
to anyone willing to pay the costs of moving.
This delay can be waived by demonstrating a financial
hardship. There are no historic districts or delays
in Alachua County.
There
is no differentiation in Alachua County and the
City of Gainesville between a deconstruction and
a demolition for permitting purposes. The total
costs of permits range from $60 to $100 for single
or two-story residential structures. The City
of Gainesville charges by the total number of
stories of a structure, and Alachua County charges
by the estimated value of the demolition work.
These permitting factors and low cost are not
conducive to encouraging deconstruction.
A
possible incentive for deconstruction under the
90-day delay ordinance is to shorten the delay
to 30 days, for example, for a “deconstruction
permit”. By shortening the delay for deconstruction,
it would be less viable to claim economic hardship
posed by the delay, some time is allowed to arrange
a building removal, and sufficient time is allowed
for deconstruction and still result in a net reduction
over the 90-day delay.
The
City of San Jose has been developing a construction
demolition debris deposit (CDDD) as a means to
encourage reuse and recycling of building materials.
This deposit, similar to the bottle deposit, requires
an upfront deposit based upon estimated waste
generation. Upon completion of the project and
documentation of reuse for distribution or transfer
to an appropriate recycling option or 50% of the
waste generated by the project, the refund is
returned. This procedure combines the demolition
permit with an economic incentive to reuse and
recycle the demolition debris.
Environmental
Issues
For
the purposes of maintaining worker health and
safety, deconstruction is a distinct activity
in EPA and OSHA regulations. Relevant environmental
and worker health and safety regulations governing
the deconstruction of buildings include: US EPA
National Emission Standards for Hazardous Air
Pollutants (NESHAPS) Asbestos Regulations (40
CFR 61, Subpart M), Occupational Health and Safety
(OSHA) Asbestos Regulations (29 CFR 1910.1001),
OSHA Lead Regulations (29 FCR 1926.26) and Classifications
of Landfills Florida Statue Rule 62-701.200 (19).
Hazardous
Materials in Deconstruction
The
NESHAPS regulation requires any commercial properties
or residential properties greater than 4 units
to have a reasonable effort to identify hazardous
materials prior to demolition or deconstruction.
The NESHAPS regulation also controls the techniques
for removal, containment, and transport of asbestos
containing materials (ACM).
The
NESHAPS regulations exempt residential structures
of 4 dwelling units or less. Residential units
demolished as part of larger public or commercial
projects such as highway construction and shopping
centers are not exempt from NESHAPS even if less
than 4 dwellings units. A group of individual
residential buildings under the same ownership
on a site is considered an installation and is
also not exempt from the NESHAPS regulations.
Hazardous materials are required to be disposed
of in a lined landfill or other disposal facility
that is permitted for those materials.
Worker
environmental safety is regulated under OSHA and
EPA guidelines regardless of the construction
activity. The PCCE utilized a certified LBP and
ACM surveyor to perform a lead-based paint (LBP)
survey and an asbestos survey when asbestos containing
materials (ACM) are visually identified during
the building assessment. The building assessment
survey also included noting the presence of fluorescent
lights, thermostats, or high-density discharge
lamps that may contain mercury or PCBs, and containers
of suspect chemicals, paint, oil, etc.
A Phase II ESA investigation is conducted
with spot testing for LBP for all structures.
LBP
is assumed in any structure built prior to and
during the period between 1970 - 1980 and OSHA
began ACM regulation in 1970. Between 83% and
86% of all homes built before 1978 in the United
States have lead-based paint in them. The older
the house, the more likely it is to contain lead-based
paint and to have a higher concentration of lead
in the paint. Houses built before 1950 pose the
greatest hazard to children because they are much
more likely to contain lead-based paint than newer
houses. (CENTERS FOR DISEASE CONTROL AND PREVENTION
(CDC))
Samples
were taken from all suspect, homogeneous ACM and
LBP surfaces on all of the structures in this
study. Polarized Light Microscopy with dispersion
staining was used to analyze the ACM samples using
US EPA Interim Method for the Determination of
Asbestos Minerals in Bulk Materials. LBP samples
are tested using the NIOSH Method #7082.
Samples were analyzed by EMSL Analytical,
Inc., Program, Greensboro, NC. The HUD minimum
threshold for the presence of lead is 0.5% Pb.
A summary of LBP findings for the structures is
provided in Table Five.
According
to the US EPA, regulated ACM (RACM) is: a) friable asbestos material; b) Category I
non-friable that has become friable; c) Category
I non-friable that will be subject to sanding,
grinding, cutting, abrading; d) Category II non-friable
that has a high probability of becoming friable
in the course of renovation or demolition activity.
Removal
and disposal of all friable asbestos must be completed
prior to demolition by a licensed professional
asbestos abatement firm. Category I non-friable
ACM (asphalt roofing shingles, floor tiles) and
Category II non-friable ACM (asbestos siding shingles,
transite board) need to be removed prior to demolition
only if they are RACM.
Category
I non-friable ACM flooring and shingle materials
and Category II non-friable ACM are not RACM and
do not have to be abated prior to demolition if
they are in good condition and not likely to become
friable during demolition. Removal of Category
I non-friable ACM is permitted according to the
Resilient Floor Covering Institute (RFCI) and
the National Roofing Contractors Association (NRCA)
aPCCEptable work practices. The NRCA association’s
recommendations are to remove asbestos shingles
by hand and lower them to the ground. Theoretically,
demolition should render all ACM to be regulated
since it is comprised of crushing, cutting, and
grinding activities. However, Category II non-friable
ACM is allowed to be demolished in place using
proper wetting and containment techniques during
the removal and transport.
Because
deconstruction poses a greater worker exposure
than mechanical demolition it is prudent to remove
all ACM, both RACM, and ACM that is in good condition.
Any materials with asbestos are also not viable
for reuse. In effect, all ACM must be abated prior
to deconstruction whether it is considered regulated
or not, which could add significant costs to a
deconstruction project over traditional demolition.
Any components that are either intended for reuse
with LBP remaining on the material or materials
that have been repainted to encapsulate the LBP
require notification that the material contains
LBP. Salvaged materials are not allowed to sit
on exposed soils where there is potential for
the LBP to leach into the soil. Salvage materials
are either moved off –site to an appropriate storage
facility, or stored on 6 mil polyethylene sheeting
and a waterproof covering. Wastes materials are
placed directly into standard 20, 10 and 8 cubic
yard roll-offs.
Table
Four - Lead and Asbestos Sample Results by Location
(6 houses)
|
|
Total
|
Floor
|
Int.
fin.
|
Roof
|
Int.
trim
|
Ext.
trim
|
Ext.
fin.
|
Insul.
|
Duct
tape
|
|
Suspect
ACM
|
50
|
27
|
17
|
3
|
0
|
0
|
1
|
1
|
1
|
|
Percentage
|
|
54.0%
|
34.0%
|
6.0%
|
|
|
2.0%
|
2.0%
|
2.0%
|
|
ACM
|
12
|
9
|
1
|
1
|
0
|
0
|
0
|
0
|
1
|
|
Percentage
|
24.0%
|
75.0%
|
8.3%
|
8.3%
|
|
|
|
|
8.3%
|
|
Suspect
LBP
|
35
|
1
|
14
|
0
|
4
|
9
|
7
|
0
|
0
|
|
Percentage
|
|
2.9%
|
40.0%
|
|
11.4%
|
25.7%
|
20.0%
|
|
|
|
LBP
|
18
|
0
|
4
|
0
|
1
|
6
|
7
|
0
|
0
|
|
Percentage
|
51.4%
|
|
22.2%
|
|
5.6%
|
33.3%
|
38.9%
|
|
|
|